The State Agency of Azerbaijan Automobile Roads continues the construction of internal roads in Fuzuli at an accelerated pace.
Report informs, citing the State Agency, that the first stage of the project involves the construction of 12 streets with a total length of 18.5 km.
Work is also underway to lay paving stones on and along sidewalks, and install lighting poles.
In addition, Fuzuli city's communication lines (water supply, sewerage, drainage pipes, gas pipeline, communication and power supply lines) are being constructed along the streets.
At present, works within the first stage of internal roads construction in Fuzuli city have been completed by 30%.